Concreting work in progress at AB42 lower bed of PL.
Concreting work in progress at AB42 lower bed of PL.
Boulder breaking work in progress at PH footing foundations.
Boulder breaking work in progress at PH footing foundations.
Pcc works in progress at control room footings of PH.
Pcc works in progress at control room footings of PH.
Pcc works in progress at control room footings of PH.
Pcc works in progress at control room footings of PH.
Formworks in progress at SP183&184 of PL.
Formworks in progress at SP183&184 of PL.
Foundation excavation working progress at AB44 of PL.
Foundation excavation working progress at AB44 of PL.
Foundations excavation work in progress at PH footings.
Foundations excavation work in progress at PH footings.
PCC works in progress at SB43 of PL.
PCC works in progress at SB43 of PL.
oundations excavation work in progress at PH and control room.
oundations excavation work in progress at PH and control room.